- Earthworks
- Concrete work; The foundation work, sub-structure and the upper structure
- Coordination of work (between main contractors and sub-contractors)
- BWIC work (Build work in Connection); namely costs prepared to overlap a job that requires extra charge
Earthworks
Note for earthwork are:
- The original ground surface peil calculated the average of peil + 0,00 (see site)
- The volume of excavation, urugan calculated net, no extras for the workplace
- Excavation unit price already includes the preparatory work, the risk of avalanches, the volume for the workplace
- Pek.urugan unit price already includes compaction layer by layer
- Exiles ground out project / bring soil from the outside has included street cleaning or if it needs to be dry pit.
- Dewatering work has included water discharge permit out location and does not interfere with the flow of water in the environment
- Unit price already includes the necessary tools and the appropriate drawings specifications
Item Earthworks
- Cleaning Location; Clearing the site of debris, grass etc dumped out the project site
- Open Cut Excavation work; Open cut excavation work, including waste at the site (location to be determined) for urugan and remaining in the exhaust to the outside site, the following aids and accessories
- Excavation work; Excavation work, including waste at the site (location to be determined) for urugan and remaining in the exhaust to the outside site, the following aids and completeness.
- Sand Fill; Sand fill is thick: 10 cm, including compaction, means of the following tools supplies equipment according to specifications and drawings.
- Anti-termite work; Anti termites on the floor and walls of the basement, including tools - tools, equipment supplies as per the specifications and drawings.
- Dewatering jobs; Dewatering System, including tools - tools, equipment supplies as per the specifications and drawings (Contractors are asked to attach a price breakdown).
Concrete work
Note Prices for Concrete Work is:
- Concrete unit price already includes all the necessary things, such as: test concrete cubes, watering, connections cessation of making concrete trenches, the slope of the level, and so on.
- Concrete unit price already includes aditive.
- The unit price of concrete has included the provision of holes sparing M / E
- steelwork unit price already includes everything needed, such as: fabrication, iron chicken legs, advocate, residual waste (waste), the wire binder / bendrad, etc.
- Formwork unit price is inclusive of all things, such as: sparing, forming oblique angles to the beam, ramp, skoor (beam amplifier, etc.)
- Unit price mix water tight intergal waterproofing additive camplast (calculated based on the volume of concrete)
- Volume is calculated net working floor (not reduced by extensive pile foundation)
- Unit price already includes the necessary tools and according to the specifications and drawings.
Concrete Work Item
- Structural Work Under; consisting of work Pile Cap and Tie beam
- Structural Work Basement; Shearwall, basement walls, plate, beams, ramp, lift pits, pit sum etc.
- Structural Work Top; Plate, beams, columns, Stairs
Please feel free to structure BQ example can be downloaded here
Engineering, Economics & Business
Aam Hermawan
No comments:
Post a Comment