Estimates are part of the QS work performed on stages of pre contract with the intent to obtain an estimate of the value of the project. the purpose of the estimation is as follows:

  • Provide guidance for planning costs to the owner and the other consultants including advice on the effect on the cost of construction due to the alternative as well as a wide design- design systems used in construction.
  • Monitor the Project Cost planning is not over-design in order to limit the cost of a predetermined (desired), as well as if it held the optimization of construction costs.
  • Creating and preparing the Bidding Documents (Terms of Implementation and Administration Bill of quantities (BQ), to be distributed to the bidders.
  • Organizing tender (anwijzing, evaluation, clarification, up to the final negotiation).
  • Prepare and check the tender documents which will be used to prepare contract documents signed between the Owner and the Contractor.

The forms are estimated as follows:

  1. Estimation Block Plan (Block Plan Estimate)
    • These estimates are based on extensive gross floor area of ​​the image concept.
    • Price per m2 building can be taken from similar projects are under way with the addition of the estimated increase in costs.
    • Price per m2 building is an estimate with some additional assumptions appropriate projects to be undertaken.
  2. Elemental estimation (elemental cost estimate)
    • At this stage the estimates have been made based on each type of work that is: Structure, Finishing, and ME.
    • Structural Work: Calculated based on the ratio of the building per m2. Eg conventional concrete ratio of 0.3 m3 / m2 and iron 160 kg / m2, flat slab concrete ratio of 0.37 m3 / m2 and iron 120 kg / m3.
    • Architectural work / Finishing: Calculated based on the image details with the use of materials based on assumptions.
    • ME Occupation: Calculated based on the ratio per m2 with the use of appropriate ratios similar projects.
  3. Estimates BQ (Detailed Cost Estimate)
    • At this stage a more detailed estimate has been made with a format like BQ.
    • Basic calculations with images DD (Desaign Development).
    • Employment structure, has been divided along the floor with a volume calculated based on the ratio of the image DD
    • Architectural work, made detail based on parts of the job (walls, floors, etc.), and to spec that does not exist can be assumed in advance.
    • ME Occupation: volume has been calculated based on the entered DD images and things that are unclear can be assumed in advance

Example Block Plan



For example make estimates can download the file here

Egnieering, Economics & Business
Aam Hermawan

2 comments:

  1. please tell me, how can I download the file. I've already followed your instruction but the file still can't open. Always drop box when I try to download.

    Thanks

    ReplyDelete
  2. I share file to dropbox, in this case you must have dropbox account :
    (if you dont have dropbox account)
    1. www.dropbox.com : create an account or sign in with google (iy you have google account) for free
    2. Sign in to our dropbox account
    3. back to this page and try to download again

    Thank you

    ReplyDelete

statistics

About Me

My photo
...... Honest-Sincere-Reliable ...... Main key in my life .... keep istiqomah ... Amiiin .....