Structure Rasio for Block Plan Estimate

At the time of making estimation block plan of course we do not yet have enough image data to calculate the volume of work items, some of which we can do is to refer to a standardized or reference to the data recapitulated in real each project so that the same can be used as a reference in determining volume calculation raiso setruktur items primarily comprising iron, formwork and concrete.

Here are the usual standards that I use
Hige Rise Building
Concrete
Plat          : 0.12 to 0.13 m3 / m2 (cubic meters of concrete per square meter of floor)
Beams     : 0.09 to 0.11 m3 / m2
Column   : 0.05 to 0.07 m3 / m2
An average of 0.26 to 0.31 m3 / m2

Reinforce bar
Plat         : 80-130 kg / m3 (kg reinforcement bars per cubic meter of concrete)
Beams     : 180-300 kg / m3
Column   : 200-350 kg / m3
An average of 160-175 kg / m3

Form Work
Plat          : 7.5 - 8 m2 / m3 (square meters form work per cubic meter of concrete)
Beams     : 6 - 9 m2 / m3
Column   : 5 - 8 m2 / m3
An average of  7 - 7.5 m2 / m3

Tie Beam
Concrete           : 0.15 m3 / m2
Reinforce bar    : 315 kg / m3
Form work        : 6 m2 / m3

Basement floor
Concrete            : 1.05% x 0.2 m3 / m2
Reinforce bar     : 150 kg / m3
Form work         : 0 m2 / m3

Upstairs
Concrete            : 0.15 x 1.05% m3 / m2
Reinforce bar     : 100-125 kg / m3
Form work         : 6 m2 / m3

Retaining Wall
Concrete             : 0.2 m3 / m2 (cubic meters of concrete per m2 wall)
Reinforce bar      : 175 kg / m3
Form work          : 9 m2 / m3

Low Rise Building
Concrete
Plat                     : 0.10 to 0.12 m3 / m2 (cubic meters of concrete per square meter of floor)
Beams                 : 0.07 to 0.10 m3 / m2
Column               : 0.04 to 0.06 m3 / m2
An average of 0.25 to 0.30 m3 / m2

Reinforce bar
Plat                     : 75-110 kg / m3 (kg reinforcement bars per cubic meter of concrete)
Beams                 : 150-220 kg / m3
Column               : 180-270 kg / m3
An average of 130-160 kg / m3

Form Work
Plat                     : 7.5 - 8 m2 / m3 (square meters form work per cubic meter of concrete)
Beams                : 6-9 m2 / m3
Column               : 5-8 m2 / m3
An average of 7 - 7.5 m2 / m3

May be useful

Engineering, Economics & Business
Aam Hermawan

No comments:

Post a Comment

statistics

About Me

My photo
...... Honest-Sincere-Reliable ...... Main key in my life .... keep istiqomah ... Amiiin .....